Whoa, so much is happening so fast. This week we poured the floor in the kitchen and basement. It took eight guys four days to mix the material, pour it, let it dry, sand it and buff it. Then make sure it was pitched correctly for drainage. It really looks awesome. Pouring the flooring was pivotal in moving the project forward. I feel like we had been pushing a giant ball up a hill and reaching the top coincided with the installation of the floor. Now the ball is rolling downhill – fast.
Don’t miss the chance to enjoy Alison at Blue Bell before the renovation. Four miles away at Alison two, things are really moving along now. Here I am standing in the bar – it won’t be long before we’re sitting at the bar and celebrating with a drink!